Both windscreens at the 90“ are now functional
Bokwalk resealed, and no longer leaks. New ceiling installed in second floor electronics shop.
Road going to dorm is finished being patched, barricades are no longer present.
Starting the week of 9/30, Ron Gayler will be living in the North apartment onsite with plans to move into the resident's house
ASAP. He is planning on working M-F, 8 hour days.
We have a dedicated KP custodian, Cruz Mancha, who will be taking care of custodial needs for the 90”, our site, and the 12m.
We currently have no weekend coverage on the mountain.
Smoke alarm upgrades are complete in the upper dorm.
Phone numbers are no longer on the 90“ white board in control room. Please find numbers in green phone binder.
New oil pressure readout on weather page in 90” control room. The power plug for this is located in second floor pier room. It's plugged into a tan power strip, and the power strip needs to be unplugged for lightning shutdown.
New trouble reports; all links on control room computers have been updated. New trouble reports look very similar to old ones.