This shows you the differences between two versions of the page.
Both sides previous revision Previous revision Next revision | Previous revision | ||
vatt:vatt_lightning_shutdown_checklist [2021/07/08 20:10] paul |
vatt:vatt_lightning_shutdown_checklist [2021/07/09 20:31] (current) paul |
||
---|---|---|---|
Line 11: | Line 11: | ||
|Control room |TCSglue: Close mirror cover | | | |Control room |TCSglue: Close mirror cover | | | ||
|Control room |TCSglue: Close dome slit | | | |Control room |TCSglue: Close dome slit | | | ||
- | | ^→Go to STEP 1 | | | + | | ^→ Go to STEP 1 | | |
| | | | | | | | | | ||
|**STEP 1**|**The following action items take place on the building' | |**STEP 1**|**The following action items take place on the building' | ||
Line 27: | Line 27: | ||
|**STEP 2**|**The following action items take place on the building' | |**STEP 2**|**The following action items take place on the building' | ||
|Lvl 1, loading dock|Turn off the UPS unit in the loading dock; turn the key to the '' | |Lvl 1, loading dock|Turn off the UPS unit in the loading dock; turn the key to the '' | ||
- | |Lvl 1, Telecom room|When the UPS is really off, go to panel A, and switch off the three bound-together 100 A circuit breakers marked '' | + | |Lvl 1, Telecom room|Go to panel A, and switch off the three bound-together 100 A circuit breakers marked '' |
|Lvl 1, loading dock|Unplug the UPS unit from the wall socket| | | |Lvl 1, loading dock|Unplug the UPS unit from the wall socket| | | ||
|Lvl 1, loading dock|Unplug building supply lines from the back of the UPS unit| | | |Lvl 1, loading dock|Unplug building supply lines from the back of the UPS unit| | | ||
Line 47: | Line 47: | ||
|Dome|**FIRST!** UNPLUG SLIT POWER and INSERT DOME SHORT | | | |Dome|**FIRST!** UNPLUG SLIT POWER and INSERT DOME SHORT | | | ||
|Dome|Insert the stow pins| | | |Dome|Insert the stow pins| | | ||
- | |Dome|Shut off everything on the telescope necessary to enter warm shutdown | | | + | |Dome|⇓ Shut off everything on the telescope necessary to enter warm shutdown: ⇓ | | |
|::: |Finder ' | |::: |Finder ' | ||
|::: |Guider camera: power down (inline switch) | | | |::: |Guider camera: power down (inline switch) | | | ||
Line 55: | Line 55: | ||
| ^Done | | | | ^Done | | | ||
| | | | | | | | | | ||
- | |**STARTUP**|Reverse the steps above| | | + | ^STARTUP |
- | |Note 1|Once you have reconnected power cords, and engaged the circuit breakers, etc., it is a good idea to start by booting up '' | + | |::: ^Use the [[vatt: |
- | |Note 2|**Booting up the servers** in the computer racks in the Instrument Room. Slide out the KVM (keyboard-video-mouse) console. ([[vatt: | + | |Note 1|Once you have reconnected power cords, and engaged the circuit breakers, etc., it is a good idea to start by booting up '' |
- | |Note 3|=) The GPS unit can take up to 10 minutes to startup fully (two blue lights: '' | + | |Note 2|Do not attempt to boot any of the other servers until '' |
- | |Note 4|Do not attempt to boot any of the other servers until '' | + | |Note 3|**Booting up the servers** in the computer racks in the Instrument Room. Slide out the KVM (keyboard-video-mouse) console. ([[vatt: |
+ | |Note 4|=) The GPS unit can take up to 10 minutes to startup fully (two blue lights: '' | ||
|Note 5|Boot '' | |Note 5|Boot '' | ||
- | |Note 6|Coming out of lightning shutdown the guide box is likely to run into communication problems. The remedy is to run the '' | + | |Note 6|Coming out of lightning shutdown the guide box is likely to run into communication problems. The remedy is to run the '' |