This shows you the differences between two versions of the page.
| Both sides previous revision Previous revision | |||
|
vatt:liquid_nitrogen_for_itl_cameras [2024/06/11 14:36] paul |
vatt:liquid_nitrogen_for_itl_cameras [2024/06/11 14:38] (current) paul |
||
|---|---|---|---|
| Line 3: | Line 3: | ||
| * then to the camera | * then to the camera | ||
| *insert the nozzle into the dewar, and attach it using the bungee cord | *insert the nozzle into the dewar, and attach it using the bungee cord | ||
| - | *start filling | + | *opening the valve, |
| - | *fill out LN2/camera log – listen for full dewar, cease flow when dewar is full | + | *fill out LN2/camera log – listen for full dewar |
| + | *cease flow when dewar is full | ||
| *disconnect LN2 filler hose from camera dewar, move storage dewar off of telescope platform and south, to dome silo wall) | *disconnect LN2 filler hose from camera dewar, move storage dewar off of telescope platform and south, to dome silo wall) | ||
| *remove camera ground wire and clip it on silo, near storage dewar | *remove camera ground wire and clip it on silo, near storage dewar | ||