| - | *start filling | + | *make sure the ground wire is connected: |
| - | *fill out LN2/camera log – listen for full dewar, cease flow when dewar is full | + | * first to the mirror cell and |
| + | * then to the camera | ||
| + | *insert the nozzle into the dewar, and attach it using the bungee cord | ||
| + | *opening the valve, | ||
| + | *fill out LN2/camera log – listen for full dewar | ||
| + | *cease flow when dewar is full | ||
| *disconnect LN2 filler hose from camera dewar, move storage dewar off of telescope platform and south, to dome silo wall) | *disconnect LN2 filler hose from camera dewar, move storage dewar off of telescope platform and south, to dome silo wall) | ||
| *remove camera ground wire and clip it on silo, near storage dewar | *remove camera ground wire and clip it on silo, near storage dewar | ||