This shows you the differences between two versions of the page.
| Next revision | Previous revision | ||
|
vatt:liquid_nitrogen_for_itl_cameras [2024/06/11 14:28] paul created |
vatt:liquid_nitrogen_for_itl_cameras [2024/06/11 14:38] (current) paul |
||
|---|---|---|---|
| Line 1: | Line 1: | ||
| - | *Start filling | + | |
| - | *fill out LN2/camera log – listen for full dewar, cease flow when dewar is full | + | * first to the mirror cell and |
| - | *disconnect LN2 filler hose from camera dewar, move storage dewar off of telescope platform and south, to dome silo wall) | + | * then to the camera |
| - | *remove camera ground wire and clip it on silo, near storage dewar | + | *insert the nozzle into the dewar, and attach it using the bungee cord |
| + | *opening the valve, start filling | ||
| + | *fill out LN2/camera log – listen for full dewar | ||
| + | *cease flow when dewar is full | ||
| + | *disconnect LN2 filler hose from camera dewar, move storage dewar off of telescope platform and south, to dome silo wall) | ||
| + | *remove camera ground wire and clip it on silo, near storage dewar | ||