- | =====90” Lightning Shutdown-Short Version===== | + | =====Bok 90” Lightning Shutdown-Short Version===== |
Last updated: 2/ | Last updated: 2/ | ||
This version is ideal for someone who is very familiar with the lightning shutdown procedure at the 90" and frequently observes here. No pictures, just the bare bones! | This version is ideal for someone who is very familiar with the lightning shutdown procedure at the 90" and frequently observes here. No pictures, just the bare bones! | ||
Line 22: | Line 22: | ||
-Unplug 3 AC power cables, 1 twist lock plug on the back wall, disconnect the BNC and Ethernet cable out of the GPS and unplug the GPS. All of these are marked by red tape. | -Unplug 3 AC power cables, 1 twist lock plug on the back wall, disconnect the BNC and Ethernet cable out of the GPS and unplug the GPS. All of these are marked by red tape. | ||
-On the 2nd floor: | -On the 2nd floor: | ||
- | -In pier room-turn off UPS in rack, unplug UPS. Remove Ethernet and unplug | + | -In pier room-turn off UPS in rack, unplug |
-In office make sure the computer and printer are off/ | -In office make sure the computer and printer are off/ | ||