User Tools

Site Tools


public:kitt_peak:bok_90:90_lightning_shutdown-long_version

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revision Previous revision
Next revision
Previous revision
public:kitt_peak:bok_90:90_lightning_shutdown-long_version [2018/09/06 14:01]
mel
public:kitt_peak:bok_90:90_lightning_shutdown-long_version [2019/05/09 11:10] (current)
davner ↷ Page moved from 90_lightning_shutdown-long_version to public:kitt_peak:bok_90:90_lightning_shutdown-long_version
Line 1: Line 1:
-=====Lightning Shutdown-Long Version, Updated 9/6/18=====+=====Lightning Shutdown-Long Version, Updated 2/15/19=====
 This version is ideal for someone who is not as familiar with the lightning shutdown procedure.  This has ALL the steps and locations of computers.  For someone who is very familiar with lightning shutdown at the 90" and who observes frequently, you might like the short version which is linked on the previous page. This version is ideal for someone who is not as familiar with the lightning shutdown procedure.  This has ALL the steps and locations of computers.  For someone who is very familiar with lightning shutdown at the 90" and who observes frequently, you might like the short version which is linked on the previous page.
  
Line 58: Line 58:
       -Click on "Primefocus Observer" or "Bok Observer" in upper right hand corner of the screen.  Click "Shutdown" in drop down menu.  This will shut down Bart.         -Click on "Primefocus Observer" or "Bok Observer" in upper right hand corner of the screen.  Click "Shutdown" in drop down menu.  This will shut down Bart.  
       -Click on the HP icon and select “PowerOff”       -Click on the HP icon and select “PowerOff”
 +    -Turn off weather computer cleanly using computer's start menu.
 ====Control Room: Near BokAux & KVM computer==== ====Control Room: Near BokAux & KVM computer====
 {{:o.jpg?nolink&300|}} {{:o.jpg?nolink&300|}}
Line 101: Line 102:
     - Turn on computer to the left of the desk on the floor.     - Turn on computer to the left of the desk on the floor.
   - Second Floor Pier Room   - Second Floor Pier Room
-    - Plug in UPS and turn on+    - Plug in UPS and turn on by pressing (I) button
   - Warm Room Cable Closet   - Warm Room Cable Closet
     -Plug in three plugs with red tape on your right as you enter the door down low     -Plug in three plugs with red tape on your right as you enter the door down low
Line 107: Line 108:
     -Plug in Brandywine NTP Server's Ethernet cable, BNC cable and power cable on west wall     -Plug in Brandywine NTP Server's Ethernet cable, BNC cable and power cable on west wall
   - Electronics Computer Rack Area   - Electronics Computer Rack Area
-    - Turn on (3) UPS units in bottom of the rack. New Console UPS-press the power button then select "On Immediately" with the arrows and OK button or it will not turn on.  +    - Turn on (3) UPS units in bottom of the rack. New Console UPS-press the power button then select "On Immediately" with the arrows and OK button or it will not turn on. Power button will go from red to white.
     - Turn on Bokpop (it should be already ON)     - Turn on Bokpop (it should be already ON)
     - Turn on Bart     - Turn on Bart
Line 119: Line 120:
   - Observers' Work Station   - Observers' Work Station
      - Turn on Azcam Xterm, log into BokCCD2 if using B&C or 90Prime.  Start the Azcam program.        - Turn on Azcam Xterm, log into BokCCD2 if using B&C or 90Prime.  Start the Azcam program.  
-     - Start Bart Xterm, log in either as Primefocus Observer if you're using 90Prime, or Bok Observer with any other instrument using appropriate passwords.  Start programs on Bart.  +     - Start Bart Xterm, log in either as Primefocus Observer if you're using 90Prime, or Bok Observer with any other instrument using appropriate passwords.  Start programs on Bart.  
 +     - Turn on weather computer by pressing the button on top of the upper left corner. 
   - At the Operators Console:   - At the Operators Console:
      - Make sure the CONTROL ROOM UPS in the Electronics Computer Rack is plugged in and turned ON (should be done already if the above steps were followed)      - Make sure the CONTROL ROOM UPS in the Electronics Computer Rack is plugged in and turned ON (should be done already if the above steps were followed)
public/kitt_peak/bok_90/90_lightning_shutdown-long_version.1536267678.txt.gz · Last modified: 2018/09/06 14:01 by mel